Polish energy storage market is not undersupplied, but rather has high financing costs

Oct 09, 2023

Polish energy storage market is not undersupplied, but rather has high financing costs
The Polish energy storage market is not undersupplied, but rather has high financing costs and needs to enter a two-year window to capitalize on these opportunities.

 

Kilian Leykam, investment manager for battery storage systems at renewable energy developer and independent power producer Aquila Clean Energy, made this point recently at the CEE Energy Storage Summit 2023 in Warsaw, Poland. The company was one of the earliest promoters of the Belgian energy storage market and is also developing storage projects in Italy, Australia and elsewhere.

In an interview with the trade press, Leykam discussed the development of the energy storage market in Central and Eastern Europe, which the company follows closely, namely Poland and the Baltic States (Lithuania, Latvia and Estonia).

 

His main point was that the Polish energy storage market is not under-supplied, but rather that project financing costs will be higher than in other markets and that developers need to enter this market in the next two years to avoid missing out.

 

How do you see the overall attractiveness of the CEE market?

 

Leykam: From a regulatory point of view, we are seeing good developments both in Poland and in the Baltic States. These energy storage markets are maturing, but obviously there are still some uncertainties, for example in the ancillary services market.

 

So we are looking for more opportunities to develop battery energy storage projects, for example, we are looking to deploy battery energy storage systems in Poland.

 

A lot of people are expecting the capacity market auction to be below the cap this year, and I think the trend is clear. Frankly, Poland, with a grid capacity of 6GW, does not look like a market with an insufficient supply of battery storage and it seems that there will be many opportunities to deploy battery storage projects. What's happening now is mostly market participants trying to figure out how to get it off the ground and grow it quickly.

 

But in terms of fundamentals, the Polish market is a good choice, and the country is committed to deploying a large number of renewable energy generation facilities and retiring coal-fired generation facilities, so Poland will be deploying more battery energy storage systems.

 

What is the current state of the energy storage market in Poland?

 

Leykam: The capacity market in Poland is growing strongly at the moment, but the proportion of revenues typically allocated to the capacity market is small. The importance of this area may decline as Poland is set to open up the ancillary services market.

 

Poland is expected to introduce ancillary services markets (FCR/AFRR) next year. We believe that these markets will offer attractive opportunities in the future.

 

In terms of current wholesale arbitrage, the Polish capacity market offers a great deal of flexibility. At the same time, the promotion and adoption of renewable energy sources is just beginning. Therefore, once Poland's lignite-fired power plants are decommissioned, we believe the Polish arbitrage market will improve further.

 

Poland is committed to phasing out coal power generation by 2049, but I think most coal plants will be phased out by 2030. I think battery storage developers need to enter the Polish market by acquiring projects in the next two years so as not to miss out on the opportunity. And energy storage projects won't really start coming online and operating until after 2026.